Notice: Function wp_enqueue_style was called incorrectly. Scripts and styles should not be registered or enqueued until the wp_enqueue_scripts, admin_enqueue_scripts, or login_enqueue_scripts hooks. This notice was triggered by the cfwccss handle. Please see Debugging in WordPress for more information. (This message was added in version 3.3.0.) in /home/rdmillercom/public_html/wp-includes/functions.php on line 6114

Notice: Function is_feed was called incorrectly. Conditional query tags do not work before the query is run. Before then, they always return false. Please see Debugging in WordPress for more information. (This message was added in version 3.1.0.) in /home/rdmillercom/public_html/wp-includes/functions.php on line 6114
Bridges – RD Miller Earthmoving and Excavations

Bridges


Permanent replacement of Timber bridges

Client: Upper Lachlan Shire Council

Date/Duration: October – December 2019

Contract Value: $827,315

Description: Project involved the replacement of bridges at Reids Flat Rd 2 / Coates Ck, Julong Rd 1 / Crookwell River, and Wilcox Rd / Clifford’s Ck. This included:

  • the demolition of existing timber bridges
  • supply and construction of concrete bridges
  • footings for abutments
  • place and pour concrete for abutments
  • place and pour concrete for decks

Parsonage Creek Bridge Formwork & Reinforcement

Client: Snowy Monaro Regional Council

Date/Duration: June – September 2019

Contract Value: $202,818

Description: Supply and deliver a prefabricated bridge formwork and reinforcement componentry system in conformance with design specifications including installation of:

  • Abutments
  • Headstocks
  • Deck panels
  • Elastometric strip bearings
  • Concrete barriers on both sides
  • Cycle barrier