Augmentation of Sewage Pump Station BB03
Client: Eurobodalla Shire Council
Date/Duration: Completed April 2022
Contract Value: $2 million
Description: The conversion of a dry well station to a wet well and refurbish the structural concrete, upgrade to three phase pumps and install new pipework. The works were completed under trying conditions with the location in a gully near a watercourse and with site constraints including groundwater @ 1m in unconfined sand, almost no access for stockpiling of wet material and work at 9m in depth in a confined space to construct the new SPS tank, pouring almost 150m3 of structural concrete into the new sewage pump station.
Adaminaby Sewage Treatment Plant Upgrade
Client: Snowy Monaro Regional Council
Date/Duration: Commenced June 2021
Contract Value: $11 million
Description: The upgrade of the Adaminaby Sewage Treatment Plant facility including:
- demolition of existing redundant infrastructure
- upgrade of access road
- siteworks including bulk earthworks, compaction, internal roadworks, water and upgraded power supply, drainage
- New inlet works
- Two SBR reactors and foul water recycling
- an inline UV disinfection system housed in new building
- a reclaimed effluent system
- a discharge pipeline and structure
- two sludge lagoons in duty/duty configuration
- a foul water pump station consisting of a wet well
- a chemical dosing system
- all pipework associated with the new plant
- design, supply and installation of all mechanical, electrical equipment
- testing, demonstrating and commissioning of the works
Horseshoe Bay beach sand removal – Bermagui
Client: Sandpiper Dredging Pty Ltd
Date/Duration: November – December 2020
Contract Value: $111,450
Description: This project involved the removal and transport of 7,000m3 of sand from Horseshoe Bay in Bermagui.
Jindabyne National Snowsports Training Centre – Air Bag Facility
Client: Office of Sport
Date/Duration: November 2020 – January 2022
Contract Value: $3.5 million
Description: This project involved the construction of a world class Airbag Training Facility for snow sport athletes to practice aerial manoeuvres in a safe and controlled environment by landing on a cushioned airbag. Construction of the facilities included:
- Clearing and demolition
- Bulk and detailed earthworks
- Construction of concrete paths and stairs
- Installation of dry snow
- Installation of landing bag
- Retaining wall structures
- Hydraulic services
- Electrical services
- Stormwater
- Landscaping, fencing and site rehabilitation
RDM was then contracted for the construction of a smaller development jump at the same facility.
Central Waste Facility – Cell 4
Client: Bega Valley Shire Council
Date/Duration: June 2020 – February 2021
Contract Value: $1.6 million
Description: Construction of a new landfill cell at Central Waste Facility including:
- bulk excavation
- final trim and surface preparation
- ground water drainage
- surface water drainage
- road extension
- culvert works
- services extensions
Central Waste Facility – New Cell – Fire Affected Materials
Client: Bega Valley Shire Council
Date/Duration: May – July 2020
Contract Value: $1.46 million
Description: Construction and operation of new Fire Affected Materials facilities including:
- Access road and haul road between facilities
- Stormwater drainage system and sediment control dam
- Asbestos landfill cell
- C&D waste sorting and processing area
- Vegetation waste sorting and processing area
- Fencing, amenities and ancillary infrastructure
- Power and water supply
- Groundwater monitoring bores
- Irrigation system (stormwater)
Bushfire Recovery – Asbestos Management
Client: Bega Valley Shire Council
Date/Duration: January 2020 – June 2020
Contract Value: $561,000
Description: Following the 2019/20 bushfires RDM was involved in assisting BVSC in the clean up and removal of asbestos from fire affected material at the Central Waste Facility.
Bombala Sewage Treatment Plant Augmentation and Upgrade
Client: Snowy Monaro Regional Council
Date/Duration: November 2019 – March 2022
Contract Value: $12.5 million
Description: The existing Bombala STP was constructed in 1969 as a trickling filter plant with a nominal capacity of 1,900 EP.
The upgrade works will involve a completely new treatment system making the old treatment plant redundant once the new works have been commissioned.
RDM is responsible for the construction of the new plant including bulk and detailed earthworks, concrete works, water and sewer pipework, kerb and gutter, roadways, pre-commissioning and all assistance in the commissioning, decommissioning and demolition of the old redundant plant infrastructure
Essential Energy Bega Depot Upgrade
Client: Essential Energy
Date/Duration: July – September 2019
Contract Value: $456,000
Description: Gabion Retaining wall, detail excavation for new concrete slabs, grated strip drain, FRP new concrete slabs x 3, FRP new stair case incl handrail, block work retaining wall.
Eden Harbour Repair
Client: Department of Industry
Date/Duration: April 2019
Contract Value: $46,557.50
Description: Design & repair work to the Eden pavement area in the lane between the Ice Plant and the Aluminium Clad building
Stage 1 Kalaru Bike Path & Water
Client: Bega Valley Shire Council
Date/Duration: February – August 2019
Contract Value: $511,000
Description: Concrete path construction including sand blinding, concrete, reinforcement, expansion and control joints, matching in service lids.
Braidwood Waste Transfer Station & Resource Recovery Station
Client: Queanbeyan-Palerang Shire Council
Date/Duration: September 2018 – August 2019
Contract Value: $4.9 million
Description: Construction of a new waste transfer station including:
- All ground slabs including concrete, lost form works reinforcement, slab thickenings/beams, strip footings and retaining walls
- All drainage including storm water pipes, pits, subsoil drainage, head walls, including aprons and rip rap, swale drains
- Construction of waste transfer station, water/sewer, fire services
- Construction of gate house, Buyback & Amenities, Weighbridge & Canopy
Malabar Horse Riding Facility
Client: Buricore
Date/Duration: September 2018 – May 2019
Contract Value: $1 million
Description: All earths works and drainage for horse arena and stables, concrete footpaths, kerb and gutter vehicle/pedestrians crossings.
Eden Footpath – Reservoir street
Client: Bega Valley Shire Council
Date/Duration: November – December 2018
Contract Value: $58,000
Description: Construction of footpath along the entire length of reservoir street. the works include additional pram ramps and connecting footpaths.
Bega TAFE Facility
Client: Joss Construction
Date/Duration: August 2018 – February 2019
Contract Value: $117,000
Description: All earthworks and concreting for shed site, install Geo-fabric liner. Construction of concrete kerbs and retaining walls.
Surf Beach Waste Management Facility
Client: Eurobodalla Shire Council
Date/Duration: May 2017 – June 2018
Contract Value: $3.7 million
Description: The project includes bulk and detailed excavation of the cell including leachate and sediment dams. It involves removing 300,000T of gravel and installation of 21,000m2 of 2mm HDPE liner.
Cooma Substation Refurbishment
Client: RCR O’Donnell Griffin Pty Ltd
Date/Duration: February – October 2017
Contract Value: $244,000
Description: The project includes concrete footings and installation of precast panels required for the refurbishment of the Cooma Essential Energy Substation.
Reeves Cold Storage Facility
Client: Reeves Family Trust
Date/Duration:
Description: All earthworks & Construction of all pavement areas, road sealing and top soiling. installation of storm water pipes & pits. Supply and construct shed and install all FR sheet insulation.
South East Regional Hospital
Client: Brookfield Multiplex
Date/Duration: 2014/15 – 90 weeks
Contract value: $8.1M
Description: RDM was subcontracted directly to perform structural concrete, stormwater and road construction works.
RDM’s scope included:
- Bulk & detailed earthworks
- All footings for slab on ground including lift wells, stair bases etc
- Slab on ground construction (10,000m2)
- Stormwater pipe & pits
- Road & car park works
- Landscaping
Bega-Cooma Transmission Line
Client: Eurobodalla Shire Council / Public Works
Date/Duration: 2012/13 – 52 weeks
RDM contract value: $6m
Description: Specialised earthworks scope included installation of 350 concrete footings with hold down bolts to accommodate the new steel powerline towers.
Brou and Moruya Landfills
Client: Essential Energy/ GHD (Superintendent), Essential Energy Major Projects (Wagga Wagga)
Date/Duration: 2012/13 – 52 weeks
RDM contract value: $6m
Description:
Specialised earthworks scope included:
- Detailed & Bulk Earthworks: 30,000m3
- Road works: 1000m2
- Pavement construction: 1000m2
- 2mm HDPE liner for the waste cell – 4000m2
Littleton Gardens, Stages 1 – 5
Client: Bega Valley Shire Council
Date/Duration: 2013/16 – 36 months
RDM contract value: $2m
Description:
Major redevelopment of the central parklands in the centre of Bega.
Demolition of existing carparks, footpaths, landscaping.
Installation of new roads, carparks, footpaths and landscaping including furniture.
Wanatta Lane Central Waste Facility
Client: Bega Valley Shire Council
Date/Duration: 2013/16 – 36 months
RDM contract value: $2m
Description: Specialised earthworks including:
- detailed & bulk earthworks: 30,000m3
- road works: 4000m2